ENVI Engineering was the Commissioning Agent for the renovation and expansion of 630,000 square feet for Klein High School.  Klein Independent School District chose Building Commissioning as their quality-oriented process for achieving, verifying, and documenting that the performance of all Klein High School building systems and assemblies meet their defined objectives and criteria.  The construction process occurred in two phases.  Systems commissioned were the mechanical and controls systems.

The scope of work accomplished by ENVI included key activities following ASHRAE Guideline 0 – The Commissioning Process.

Commissioning Project
Klein, Texas

 

Education: PK – 12
630,000 square feet